Thought I would post some pics and commentary on some jobs I have done recently.

This project was an interesting one. A frozen food processing facility was installing a new cooler. Problem was the building had a high water table underneath the slab where the new cooler was going. Our job was to excavate 22" of very sticky, very wet clay and replace with woven geotextile fabric and #57 stone to separate the water from the -10 F degree cooler that would sitting on top of it. The...